Operator in SSA had outdated and infrequent production well test data due to the crane load and space constraints on small unmanned platforms
Existing platform separators not suitable for brownfield production conditions
Operator was relying on simulations and conventional downhole data-based sampling for production allocation, discrepancies with shared fiscal metering were evident
Lack of representative Pressure Volume Temperature (PVT) data
Production from diverse reservoirs, from undersaturated to mature and post-mature, with flow regime challenges such as foam, heavy oil, emulsions, and slugging
Total gas production essential to design upcoming LNG plant
Expro Excellence
Expro provided a compact MPFM testing skid along with Mini Separator for onsite PVT analysis
Seamless flareless production testing of over 40 wells across 8 platforms with diverse Gas Oil Ratios (GOR) of 6 to 8250 Sm3/Sm3, API gravity of 14-52 and water cuts ranging from 0% to 96%
Wide turndown multiphase measurement solution provided across the field with single MPFM and Mini Separator unit
Testing performed around the clock with no HSE events
Value to Client
Accurate production allocation data across all tested platforms, validation of water cut sample points, and verification of simulation models
Reduced testing equipment load (less than 3000 kilograms per lift) and footprint (less than 4-meter square) minimized personnel requirements and elimination of flaring and carbon emissions
Customer leveraged well test data to perform well intervention and workovers such as acid wash, downhole gauge replacement
Asphaltene issue identified on a well with no flow measurement
Contact