Decommissioning of operator's development in the Central North Sea
The data gathering campaign included an eight well scope with the following objectives: perform wireline on eight wells; drift completion tubing and run pressure/temperature gauges; set bridge plugs in completion tubing in five wells; evaluate the quality of the liner cement bond in one well
A full plug and abandonment campaign will commence in Summer 2017
Expro Excellence
Expro was the provider of choice due to track record of operational delivery and wireline expertise previously demonstrated
Lead contractor, project management of Expro and third-party incumbent service providers: effective integration of multiple partners to cover logging, wireline conveyance, plugs, tractor, and camera services
Integrated multi-skill crew to optimise platform personnel on board
Completed scope of work for eight interventions ahead of schedule in 37.50 days (P10 target of 43.50 days)
Efficient pre-planning: leadership engagement sessions; attendance at 'value creation' events; pre-work visit to establish rig-up arrangements and establish safe systems of work permit packs; daily interaction with operator's team leads and third-party incumbents
Collaboration success with effective teamwork
Value to Client
Zero HSE incidents
"Right first time" delivery
Delivered campaign ahead of time and under budget - six days ahead of target due to efficient execution
Saved 33% against AFE from value creation ideas
Saved 27% against AFE from operational performance