Expro have a long-standing relationship with Shell and were approached to provide a suite of services to the Corrib Project, offshore North-West Ireland (Atlantic Ocean), to achieve the successful completion of the gas well to allow production to the Irish grid via a new gas facility
To complete within challenging conditions (particularly weather), in a tight timeframe, whilst in a remote location
Expro Excellence
Expro’s ‘first time right’ approach ensured compliance with tight timeframe
Approximately 737 operational hours with zero Expro NPT
Subsea, slickline, well test and sampling teams all involved – seamless transition between phases with all product lines working in unison
Flexible approach by Expro overcame logistical issues caused by the remote location
Successful cutting trials completed with SSTT on 2” coil tubing and wireline
16 wireline runs
Well test with maximum gas rate of 116 MMscf/day
On-site fluid sampling
Value to Client
Expro’s excellent performance allowed Shell to complete the Corrib Project as required by the Irish Government – late completion may have delayed the project significantly
When operational, the facility contributes up to 60% of Ireland’s gas requirement