Our client’s previous cementing strategy resulted in WOC on conductor and time spent drilling out conventional shoetracks on the 16” section. The client also required a clean out run if opting to drill a pilot hole out of the 16” shoe
Expro Excellence
Expro’s SeaCure® delivered a quality cement job with the added benefit of rapid cement hydration technology, QuikCure® reducing WOC on the conductor to four hours. The zero shoetrack solution also allowed for a simple and reliable drill out
Value to Client
Reduced conductor WOC time to four hours, with downhole temperature logger showing cement going through hydration process after just two hours
1,200psi (83bar) surface casing pressure test carried out on green cement
Surface casing cement job displacement volume reduced to 29 bbls (~5m3) due to stabbed in inner string conduit
Simple and reliable drill out of both the 24” and 16” shoes
CoreCure® downhole cement sample confirming hard, good quality cement at the shoe