Wireless controlled technologies eliminate 'Working at Height' and 'Red-Zone Exposure' whilst running, floating & cementing casing on a Semi-Submersible in the North Sea
A major operator identified multiple challenges whilst planning to run a casing string in the 12-1/4” open hole of an ERD Well with a step-out ratio of 2.23 (6,378 ft step-out over just 2,858 ft TVD)
Computer modelling predicted that excessive drag in the horizontal section would prevent the casing being run conventionally beyond 5,000 ft measured
In order to run the casing to the intended measured depth of 8,400ft, the casing would have to be floated in hole using the ‘mud over air’ casing floatation method
Objectives
Hands-free casing running o Mitigate risks of ‘Slip-Slap’
Vent air whilst filling the casing after the floatation collar is burst
Rig-Up the cement hose with no personnel in the Red Zone and no working at height
Launch two darts with no personnel in the Red Zone and no working at height
Catch and contain the darts downhole during the cement job, recover to surface post job
Remove personnel from the Red Zone throughout the entire job
Expro Excellence
Expro provided specialist equipment and services that enabled all objectives to be achieved
Seven technologies with proven track record were used to maximize safety and efficiency:
FA-1® Top Drive Casing Running Tool (CRT)
Single Joint Horseshoe Elevator (SJHSE)
14 3/8 Power Tong
Radio Remote Control Tong Control System
Tong Pusher Arm (TPA)
Blackhawk® Top Drive Cement Head
Skyhook® Wireless Cement Line Make-Up Device
MULTICATCH™ Dart Catcher System
One new assembly was designed and manufactured to vent & fill the Casing
11 3/4 Vent Sub Assembly
One conventional tool was modified to mitigate risk of equipment damage during ‘Slip-Slap’
Rotary Adaptor Ring
A subtle change to the Power Tong rig-up would ensure safe operations during ‘Slip-Slap’
Value to Client
All operations were completed with no incidents and zero NPT
Meticulous planning, preparation and execution helped lower risks ALARP
Risks specific to casing floatation were identified, well managed and successfully mitigated
The string was run to the planned TD (8,227ft), enabling production potential to be maximized
The floatation collar was ruptured per plan with no unexpected outcomes
Venting the trapped air whilst simultaneously filling with mud minimized rig time
The string was cemented with no losses, and successfully pressure tested to 4,100psi
Expro technologies reduced and eliminated risks to personal, equipment and operations
Expro’s high quality of service helped the client complete a safe and very successful job