Case Study

SeaCure zero shoetrack solution undergauge - Cementing Tech

In Brief

SeaCure® zero shoetrack solution enables safe and reliable undergauge drill ahead 

Customer Challenges

  • Earlier under-gauge drill out of 20” surface casing can cause stuck BHA or even requiring a 17-1/2” clean out trip

Expro Excellence

  • Clinical execution SeaCure® Cementing eliminates SSR plugs and shoetrack enabling slim drill ahead

Value to Client

  • Saved SSR plugs, shoetrack, cement head and clean-out bit/BHA costs
  • Shoe drilled out under gauge in 15 minutes
  • Reduced cement job displacement volume by >30m3
  • Saved more than ten hours of rig time
  • Saved more than 65MT in CO2 emissions
  • Delivered zero NPT service execution

Contact

For further information, please contact wellconstruction@expro.com.