To reduce conductor WOC time and achieve a quality primary cement job on the first string of this high profile well
Expro Excellence
SeaCure® delivering a quality primary cement job with the added benefit of rapid cement hydration technology, QuikCure® to reduce WOC on conductor to ~ 5hrs. The zero shoetrack solution also allowed for a simple and reliable drill out of the 30” shoe
Value to Client
Reduced conductor WOC time to ~5 hours
Downhole temperature logger in BHA showing heat of hydration of cement ~2.5 hours after placement
Cement job displacement volume reduced to 8bbls (1.3 m3)
Simple and reliable drill ahead with shoe drilling out in 40 minutes
CoreCure® downhole cement sample confirming hard, good quality cement at the shoe