Case Study

CoilHose™ unloads two offshore wells under the Hydra Integrated Solution

In Brief

CoilHose™ delivers efficient, low‑risk unloading of two offshore wells, showcasing the performance and commercial value of the Hydra Integrated Solution

Region

Customer Challenges

  • Newly drilled offshore wells in Indonesia are subject to significant operational constraints arising from limited deck space, reduced crane capacity, and stringent economic pressures to minimize intervention-related expenditure 
  • Two completed wells required fluid displacement to reservoir depth, as the sensitive reservoir formation could only withstand minimal fluid ingress. The primary challenge for the customer was to successfully unload these wells at depths of 2,500 m and 2,200 m prior to sliding side door (SSD) activation 
  • These platforms, designed as minimalistic installations, necessitate an integrated approach that enables multiple services to be executed from a single operational footprint. The restricted deck area and limited accommodation capacity render traditional multi-supplier intervention models impractical 
  • The campaign therefore required a consolidated intervention solution capable of delivering Slickline, E-Line, and efficient displacement and unloading of completion fluids within the platform’s operational constraints

Expro Excellence

  • Expro addressed these challenges through deployment of the Hydra solution, a fully integrated multi-intervention system consolidating Slickline, E-Line, and well unloading services into one compact package. Using CoilHose™ technology in place of conventional Coiled Tubing eliminated the requirement for multiple contractor spreads 
  • The Hydra solution combined mechanical slickline for drift runs, E-line for SSD manipulation with stroker, and CoilHose™ for nitrogen unloading into a single integrated intervention system, with all services rigged up and deployed using the Well Intervention mast. Modular front-end packages enabled rapid transitions between services while utilizing the same mast infrastructure, reducing footprint and POB and improving operational efficiency. Conventional standalone packages would have required multiple mobilizations and repeated rig-up and rig-down activities, significantly extending the campaign

Value to Client

  • Excellent cooperation and collaboration between Expro and the client’s intervention team during the project 
  • The Hydra solution substantially enhanced rig-up and rig-down efficiency, enabling faster execution of operations supported by a multidisciplinary team working with a reduced POB Integrated approach 
  • The operation successfully recovered 110 bbl and 161 bbl of well fluid from the respective wells, enabling immediate production start-up at 20 MMSCFD 
  •  The two well completion project was completed without downtime, NPT, or HSEQ incidents, thereby delivering optimal value to the client 
  • The client now regards CoilHose™ as the preferred method for nitrogen unloading operations