As one of the longest producing fields in the UKCS, the formation of scale is a continuous challenge that the operator is required to manage
Two types of scale that are present within the field are calcium carbonate and barium sulphate
Conventional methods such as milling techniques or chemical dissolvers are often only considered once production loss has been experienced
A scale inhibition program was implemented to proactively prevent the formation of scale and would require routine hydraulic intervention of the wells
Ageing assets provide challenges with POB, weight limitations, deck space and therefore an integrated approach would be required
Electrification of pumping spread was key to its location within the platform zoning restrictions
Expro Excellence
Expro delivered a multi-disciplined crew structure combining both Mechanical and Hydraulic Intervention Specialists as part of the core crew to deliver across all assets in the field
A bespoke pumping system was designed to meet the customer requirements
The system consisted of a small footprint, lightweight design that could be integrated into the zoned areas within the centre of the platform adjacent to the wells themselves
Pumps were electric driven using existing platform power contributing to a lower carbon footprint than conventional diesel driven units
Expro’s Hydraulic Intervention services were extended to a second field consisting of two producing assets that the customers owned and operated
Value to Client
Continuous production is maintained through careful planning and execution with 100% uptime across all Hydraulic Interventions conducted to date
Specifications of the pumping system is such that a planned change in chemical design could easily be accommodated ensuring intervention timings were minimized
A combination of multi-disciplined crew structure and blended contract management provide the customer with enhanced reactions times and more precise forward planning when combining both Mechanical and Hydraulic Intervention across their assets